Billing Schedules for FY25 Delivery and Capacity Charges

  1. Invoice Mailing – No later than the 10th working day of the month following the Invoice Month.
  2. Payment Due – By 2:00 p.m. on the 10th business day of the month following Invoice Mailing.
  3. Business Day – Means any day other than a Saturday, Sunday, a Bank Holiday*, or a Water Authority Holiday.
  4. Bank Holidays* – That are not Water Authority holidays are counted as business days (i.e., Columbus Day is a Water Authority business day).
  5. Capacity Charges – Capacity charges collected by a Member Agency during the prior three (3) calendar months are due on or before 2:00 p.m. of the last day of the month of January, April, July and October of each year. If the payment due date falls on a day that is not a Water Authority business day, the payment is due the next business day before 2:00 p.m. or is delinquent.
  6. Delinquency Charge – Payment is to be made by the stated Due Date. The amount due shall be delinquent if not received in investable funds in full by 2:00 p.m. on the Due Date. There will be a delinquency charge of two percent (2%) on the unpaid amount for each month, or any portion thereof, that the payment remains delinquent. If the delinquency does not exceed five (5) business days, the delinquency charge shall be reduced to one percent (1%) of the delinquent amount. A payment remains delinquent and will continue to be assessed a delinquency charge on the unpaid amount so long as any portion of the original payment amount or of the delinquency charge, remains unpaid. Any protest of a payment must be filled concurrently with full payment of the amount due.
  7. In September 2022, the Board adopted a policy permitting the General Manager to waive penalties and interest on any delinquent payment of fees, rates, or charges by a Member Agency or other persons so long as the amount does not exceed $5,000, and as to Member Agencies: (1) as to water bills, payment was not more than three calendar days delinquent; and (2) as to capacity charge bills, payment was not more than thirty (30) days delinquent. Notwithstanding the foregoing, if a Member Agency has been delinquent more than once in the prior 12 months, the Board must approve the waiver.
Water Delivery

Water Delivery Charges

Invoice MonthInvoice Mailing (1)(3)(4)Payment Due (3)(4)(5)(6)
July 2024August 15, 2024September 16, 2024
August 2024September 17, 2024October 14, 2024
September 2024October 15, 2024November 15, 2024
October 2024November 18, 2024December 13, 2024
November 2024December 16, 2024January 15, 2025
December 2024January 16, 2025February 14, 2025
January 2025February 18, 2025March 14, 2025
February 2025March 17, 2025April 14, 2025
March 2025April 15, 2025May 14, 2025
April 2025May 15, 2025June 13, 2025
May 2025June 16, 2025July 15, 2025
June 2025July 15, 2025August 14, 2025

Capacity

Capacity Charges

Quarter EndedPayment Due (3)(4)(5)(6)
September 2024October 31, 2024
December 2024January 31, 2025
March 2025April 30, 2025
June 2025July 31, 2025