Project
|
Estimated Value/Advertisement Date/Contacts
|
Other Project Information
|
Trades
|
| Emergency Storage Projects – Access Roads, and Marina Grading for San Vicente Dam Raise (Package 2) Drill, blast, and excavate hard rocks to prepare for construction of marina access roads; construct permanent access roads of approximately 3/4 miles in length and 25 feet in width with asphalt pavement; and process about 250,000 cubic yards of rock/soil mix for mass grading for the upcoming marina facilities construction.
|
Estimated Value $ 20,000,000.00 - $ 30,000,000.00
Estimated Advertisement Date: 10/00/2008-- Bid Opening/Proposal Due Date: --
Contacts Jim Zhou
Design Manager
jzhou@sdcwa.org
Ph (858) 522-6837
Fax (858) 268-7802
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
Other Trade General Contractors, Surveying, drill/blasting/(rock) excavation, rock processing, A/C paving, earth
|
| Mission Trails Pipeline Tunnel and Vent Demolition The project consists of a 92-inch diameter, 5,000-foot pipeline tunnel from north of Elliot Vent Number 1 to south of Elliot Vent Number 4, and appurtenant facilities for the untreated water system. The Mission Trails Pipeline Tunnel will relieve hydraulic constraints along the Second Aqueduct located North of Mission Gorge and will result in eliminating up to ten Elliot Vents through Mission Trails Regional Park.
|
Estimated Value $ 35,000,000.00 - $ 41,500,000.00
Estimated Advertisement Date: 04-28-2008 Bid Opening/Proposal Due Date: 06-17-2008
Contacts Mike Conner
Contract Manager
mconner@sdcwa.org
Ph (858) 522-6856
Fax (858) 522-6568
Melissa Retener
Contract Technician
mretener@sdcwa.org
Ph (858) 522-6804
Fax (858) 522-6568
|
Project Fact Sheet
Contract Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades General Contractors; General Engineering; Landscape; Structural Contractors; Welders
Other Trade Tunnel Construction
|
| Mission Trails Flow Regulatory Structure II The project consists of a 12 million gallon buried concrete tank and appurtenant facilities for the untreated water system. There will be two 6MG basins with a hopper type bottom. A small building will provide access, ventilation and instrumentation.
|
Estimated Value $ 28,500,000.00 - $ 33,500,000.00
Estimated Advertisement Date: 07-00-2008 Bid Opening/Proposal Due Date: --
Contacts Mike Conner
Contract Manager
mconner@sdcwa.org
Ph (858)522-6856
Fax (858)268-7802
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades Electrical; General Contractors; General Engineering; Landscape; Mechanical; Structural Contractors; Welders
|
| East County Regional Treated Water Improvements Program - Otay Flow Control Facility The project will expand the capacity of the existing Otay 14 Flow Control Facility from 8 mgd to 16 mgd. The facility is comprised of a partially below grade structure with inlet and outlet piping. The address of the facility is 290 South. Third Street, El Cajon, CA 92019.
This expansion will require upsizing about 75’ of 16” piping to 20”. Several mechanical equipment/appurtenances will require replacement including isolation, control, and air valves, venturi flowmeter, valve electric actuator, and minor instrumentation. The existing facility will be subject to civil, mechanical and electrical work. Minor structural modifications to the building will also be required.
Construction is expected to commence in October 2008 and be completed by August 2009.
|
Estimated Value $ 300,000.00
Estimated Advertisement Date: 08-00-2008 Bid Opening/Proposal Due Date: --
Contacts Jennifer Farrell
Ph (619)725-5075
Fax (858)268-7802
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades Electrical; General Engineering; Mechanical; Welders
|
SERVICES: PROFESSIONAL and NON-PROFESSIONAL
|
|
|
|
Project
|
Estimated Value/Advertisement Date/Contacts
|
Other Project Information
|
Trades
|
| Support for Water Conservation Regional Stakeholder Process Outreach, facilitation and logistical support related to the Water Authority’s water conservation regional stakeholder process. Pre-Proposal Meeting: Thursday, March 20 at 1:30 p.m. in the Library Conference Room of the San Diego County Water Authority
|
Estimated Value
Estimated Advertisement Date: 3/12/08-- Bid Opening/Proposal Due Date: 4/3/08--
Contacts Kelly Mooney
kmooney@sdcwa.org
Ph 858-522-6600
Fax 858-268-7881
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
|
| Corrosion Engineering and Technician Services These positions will be used to assist the Water Authority’s Aqueduct Protection Program
in corrosion assessment and prevention of more than 280 miles of pipelines, 100 service
connections, four pumping plants, and two low-head power plants. Tasks to be
performed include but are not limited to the following: field investigations, testing,
design of cathodic protection systems, review, install, and repair cathodic protection
systems, and internal inspection of large diameter pipelines.
|
Estimated Value $ 2,000,000.00
Estimated Advertisement Date: 3/14/08-- Bid Opening/Proposal Due Date: 4/8/08--
Contacts Aleicia Rangel
Contract Technician
arangel@sdcwa.org
Ph 760-233-3242
Fax 760-480-9867
|
Project Fact Sheet
Contract Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
Other Trade Corrosion Engineering
|
| Project Design Review and Environmental Compliance Monitoring Services for the Carryover Storage and San Vicente Dam Raise Project Contractor will provide design review services during the final design phases of the project and environmental compliance monitoring support services during construction. Services will include monitoring of construction activities to ensure compliance with adopted project mitigation measures, design features, and permit requirements.
|
Estimated Value $ 800,000.00 - $ 1,000,000.00
Estimated Advertisement Date: 02-15-2008 Bid Opening/Proposal Due Date: 03-17-2008
Contacts Paul J. Amberg
Environmental Program Manager
Ph (858)522-6822
Fax (858)268-7881
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
Other Trade Environmental Compliance Monitors, Biological Resources Monitors, Cultural Resources Monitors, Noise
|
| Design Review - As Needed Services * The Water Authority may use its statement of qualifications database to shortlist for these opportunities.
|
Estimated Value $ 850,000.00
Estimated Advertisement Date: 05-01-2008 Bid Opening/Proposal Due Date: --
Contacts Ilene
Story
istory@sdcwa.org
Ph 858-522-6829
Fax 858-268-7802
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades Electrical; General Engineering; Mechanical; Structural Contractors
Other Trade Civil, Architectual, Instrumentation and Controls, and Corrosion
|
| Electrical Design and Instrumentation and Controls As-Needed Services
* The Water Authority may use its statement of qualifications database to shortlist for these opportunities.
|
Estimated Value $ 500,000.00
Estimated Advertisement Date: 05-01-2008 Bid Opening/Proposal Due Date: --
Contacts Ilene
Story
istory@sdcwa.org
Ph 858-522-6829
Fax 858-268-7802
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades Electrical
Other Trade Instrumentation and Controls
|
| Remote Monitoring of Cathodic Protection Facilities The remote monitoring system for the Water Authority's Impressed Current Cathodic Protection and Galvanic Anode Cathodic Protection facilities will allow a single person to monitor the cathodic protection on the Water Authority's pipelines remotely by accessing a computer.
|
Estimated Value $ 300,000.00
Estimated Advertisement Date: 05-12-2008 Bid Opening/Proposal Due Date: 06-02-2008
Contacts Aleicia Rangel
Senior Office Assistant
arangel@sdcwa.org
Ph (760)233-3242
Fax (760)480-9867
|
Project Fact Sheet
Contract Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
Other Trade Corrosion Engineering
|
| Emergency Storage Projects - Pipeline 3 Interconnect - DM Design Contractor – Prepare a design for a new ESP pump station on Pipeline 3 of approximately 11.4 cfs capacity.
|
Estimated Value $ 135,000.00
Estimated Advertisement Date: 08-00-2008 Bid Opening/Proposal Due Date: --
Contacts Bill Wood
Project Manager
BWood@contractors.sdcwa.org
Ph (619)543-4307
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
Other Trade Civil; Hydraulic; Mechanical; Electrical; Instrumentation and Controls
|
| Pipeline 3 Relining Scripps Ranch to SR-52 CM Construction Manager for Relining of approcimately 24,000 linear fet of 69-inch prestressed concrete cylinder pipe with steel liners inserted in up to 16 access portals
|
Estimated Value - $ 3,000,000.00
Estimated Advertisement Date: 08-00-2008 Bid Opening/Proposal Due Date: --
Contacts Jennifer Farrell
Contract Technician
Jfarrell@contractors.sdcwa.org
Ph (619)725-5075
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades Carpenter; Construction Inspector; General Contractors
|
| Emergency Operations Center-Design Review and edit 60 percent design as necessary, continue the architectural design and construction support services for an Emergency Controls Center. The Emergency Controls Center will be approximately 6,500 square feet and will house the relocated Aqueduct Control Room, Emergency Operations Center and associated staff offices. This facility will be designed as an "Essential Facility".
|
Estimated Value
Estimated Advertisement Date: 09-00-2008 Bid Opening/Proposal Due Date: --
Contacts Jennifer Farrell
Contract Technician
Jfarrell@contractors.sdcwa.org
Ph (619)725-5075
Fax (619)725-5079
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
|
| ESP- Operations Center Building upgrade Review and edit 60 percent design as necessary, and continue the design and construction support services for the upgrade of the Escondido Operations Center and the the seismic upgrade of a vehicle maintenance warehouse, both are located at 610 West 5th Avenue, Escondido, CA 92025. The vechicle maintenance warehouse is an 11,250 square foot warehouse that will be seismically upgraded to an "Essential Service Facility"
|
Estimated Value
Estimated Advertisement Date: 09-00-2008 Bid Opening/Proposal Due Date: --
Contacts Jennifer Farrell
Contract Technician
Jfarrell@contractors.sdcwa.org
Ph (619)725-5075
Fax (619)725-5079
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
|
| Miramar Pump Station Rehabilitation Design Contractor- Prepare design for rehabilitation of the existing Miramar Pump Station
|
Estimated Value $ 110,000.00
Estimated Advertisement Date: 09-00-2008 Bid Opening/Proposal Due Date: --
Contacts Bill Wood
Project Manager
BWood@contractors.sdcwa.org
Ph (619)543-4307
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades General Engineering
|
| North County Flow Control Facilities Construction Contractor- Construct three flow control facilities in the Fallbrook-Rainbow area of San Diego County
|
Estimated Value $ 580,000.00
Estimated Advertisement Date: 12-00-2008 Bid Opening/Proposal Due Date: --
Contacts Bill Wood
Project Manager
BWood@contractors.sdcwa.org
Ph (619)543-4307
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades General Engineering Contractors
|
| Mechanical Design Pump Station/ Flow Control Facilities As-Needed Services
|
Estimated Value $ 400,000.00
Estimated Advertisement Date: 12-01-2008 Bid Opening/Proposal Due Date: --
Contacts Ilene
Story
istory@sdcwa.org
Ph 858-522-6829
Fax 858-268-7802
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades General Engineering; Mechanical
Other Trade Civil
|
| Relining Project Miramar Hill to Scripps Ranch Design services needed
|
Estimated Value $ 350,000.00
Estimated Advertisement Date: 6-01-2008 Bid Opening/Proposal Due Date: --
Contacts Jennifer Farrell
Jfarrell@contractors.sdcwa.org
Ph (619)725-5075
Fax (619)725-5079
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
|
| Emergency Storage Projects - Pump Station at Pipeline 3 - DM Design Contractor – Prepare a design for a short ESP interconnect pipeline between Pipeline 3 and Pipelines 1 and 2.
|
Estimated Value $ 190,000.00
Estimated Advertisement Date: 8-00-2008 Bid Opening/Proposal Due Date: --
Contacts Bill Wood
Ph (619)543-4307
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
Other Trade Civil; Hydraulic; Mechanical; Electrical; Instrumentation and Controls
|
| Emergency Storage Projects - Pump Station at Pipeline 4 - DM Design Management ContractorDesign Contractor – Prepare a design for a new ESP pump station on Pipeline 4.
|
Estimated Value $ 250,000.00
Estimated Advertisement Date: 8-00-2008 Bid Opening/Proposal Due Date: --
Contacts Bill Wood
Ph (619)543-4307
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
Other Trade Civil; Hydraulic; Mechanical; Electrical; Instrumentation and Controls
|
| Emergency Storage Projects - Pipeline 3 Interconnect - CM Construction Management Contractor.
|
Estimated Value $ 185,000.00
Estimated Advertisement Date: 01-00-2009 Bid Opening/Proposal Due Date: --
Contacts Matt Smith
Ph (619)543-4305
Fax (858)268-7802
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
Other Trade Construction Management; Civil; Mechanical; Geotechnical
|
| Emergency Storage Projects - Pump Station at Pipeline 3 - CM Construction Management Contractor.
|
Estimated Value $ 265,000.00
Estimated Advertisement Date: 01-00-2009 Bid Opening/Proposal Due Date: --
Contacts Matt Smith
Ph (619)543-4305
Fax (858)268-7802
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
Other Trade Construction Management; Civil; Mechanical; Geotechnical
|
| Emergency Storage Projects - Pump Station at Pipeline 4 - CM Construction Management Contractor
|
Estimated Value $ 330,000.00
Estimated Advertisement Date: 01-00-2009 Bid Opening/Proposal Due Date: --
Contacts Matt Smith
Ph (619)543-4305
Fax (858) 269-7802
|
Project Fact Sheet
Project Documents Order Form
Plan Holders List
Questions and Answers
Links to Electronics Contract Documents:
The Network Ebidboard
|
Anticipated Trades
Other Trade Construction Management, Civil, Mechanical, Geotechnical
|
|
Print
(Note: To print this web page, please set your page orientation to
landscape.)
|