San Diego County Water Authority
San Diego County Water Authority
About Us
Water Management
SDCWA Infrastructure
SDCWA News Publications
Board of Directors
Education
Opportunities
Contact Us
San Diego County Water Authority

Photographic Tour

Construction of the Lake Hodges Projects began in 2005 and is anticipated to be completed in late 2010. The construction has four components:

• Pipeline Tunnel – a 10-foot diameter underground pipeline, contained in a 1.25 mile long tunnel, connecting the two reservoirs

• Pump Station – a pump station to move water back and forth between the two reservoirs and generate electricity

• Electrical Switchyard – an electrical switchyard providing electricity to the pump station and sending electricity from the pump station to a local transmission system, SDG&E will build one part and the Water Authority will build adjacent equipment

• Inlet-outlet Structure – an inlet-outlet structure below the water surface that draws and discharges water between the Hodges Reservoir and the pump station

Diagram of Lake Hodges Projects Components

Pipeline Tunnel
Completed in spring 2007, the pipeline tunnel is 1.25 miles-long and contains a 10-foot diameter steel pipeline that rises 770 feet in elevation from Hodges Reservoir to Olivenhain Reservoir.

Water will flow back and forth between Hodges and Olivenhain Reservoirs within this 10-foot diameter steel pipe. The pipe’s epoxy coat protects the steel pipe from internal corrosion. In total, 148 sections of pipe were used to complete the tunnel.

 

This is a “pipe carrier.” It was used to lift and place the steel pipe within the 1.25-mile-long pipeline tunnel

 

A mucking machine pushes the “pipe carrier” into the pipeline tunnel.

 

In this image, the pipe section is placed within the pipeline tunnel and attached to another installed section of pipe.

 

The pipe section is secured inside the pipeline tunnel using timber bracing. The bracing keeps the pipe from moving and allows the area between the outside of the pipe and the tunnel wall to be backfilled with grout.

 

One by one, each section of pipe is welded together and forms the pipeline inside the tunnel.

 

Once welded together, the space between the 12-foot diameter tunnel and the 10-foot diameter pipeline is filled with grout. Grout is a fluid material injected into soil, rock, concrete, or other construction material. Once hardened, it forms a permanent impervious, watertight bond that provides structural strength to the pipeline tunnel. This picture shows the grout being pumped through a grout port installed in the pipe.

 

Construction crews inspect the inside of the pipeline tunnel prior to completion in spring 2007.

 

Once completed, the pipeline tunnel was sealed in May 2007. The seal will be removed when the pump station contractor connects the pump station piping.


Pump Station
The Hodges Pump Station will extend 12-stories underground and house two 28,000 horsepower pump turbines that will generate 40 megawatts of electricity as water flows down the pipeline tunnel from Olivenhain Reservoir to Hodges Reservoir. Electricity generated by the pump turbines will be transmitted to an outdoor switchyard, then to a 69kV, ¼-mile-long power line that will connect to the existing local transmission system.

Construction equipment and materials used in the tunneling process are lowered and lifted in and out of the pump station pit using a crane.

 

Looking down from the top pump station pit, you can see the excavators removing material that has been blasted. The material is put in a dumpster-sized bucket and hauled out of the pit using a crane.

 

photo

At the bottom of the pit that will house the pump station, construction workers drill pilot holes horizontally towards Lake Hodges. This construction method is referred to as drill & blast method, in which pilot holes are drilled for explosive charges. Once the explosive charges are set-off, the resulting debris is carried out and the process is repeated.

 

photo

The two-pronged inlet/outlet tunnel will draw or discharge water back and forth from the inlet/outlet structure, located at the bottom of Hodges Reservoir, and the pump station.

 

After construction crews completed excavation of the 12-story Hodges Pump Station pit in June 2007, construction of the pump station’s foundations, walls, and floors started. Here, a construction worker places steel reinforcing bars within the Pump Station floor. The reinforcing bars are encased within concrete to strengthen and hold the concrete together.

 

Construction crews started pouring the foundation of the pump station in June 2007. Here, concrete is lowered in a large bucket and poured onto the steel framework.

 

Another method of delivering concrete form the top of the pump station excavation to lower sections was the use of a concrete pump truck.

 

As concrete is poured, a construction worker smoothes-over and levels the concrete with an extension trowel.

 

Here workers smooth and level a floor within the pump station.

 

As construction continued within the pump station, steel reinforced walls were poured.

 

Some steel-reinforced concrete walls within the pump station reached ground level in April 2008.

 

As concrete work on floors and walls took place, some of the water pipes and equipment was installed. This image captures the installation of equipment that now houses the two pump turbines. The pump turbines will generate electricity as water flows from Olivenhain into Hodges Reservoir. The pump turbines will also send water from Hodges Reservoir uphill 1.25 miles to Olivenhain Reservoir.

 

Equipment for the Lake Hodges Projects has come from all over the world. This 98-ton section of pipe is 21 feet in length and width and arrived on an oversized delivery truck from Fontana, Calif. in May 2009. It connects the pump station to the 1.25-mile-long pipeline between the Hodges and Olivenhain reservoirs and split the tunnel’s water flow to feed two pump turbines housed in the pump station.

   

This long section of pipe is part of a connecting series of pipes that link the Y-shaped bifurcated pipe that enters the pump station with the pipeline that connects to the Olivenhain Reservoir. The wood inside reinforces the pipe, keeping the pipe round, and is removed once the pipeline is encased with concrete.

   

This section of pipe connects to the 10-foot diameter pipeline already encased in the 1.25 mile long tunnel that connects to the Olivenhain Reservoir.

   
Several maintenance hatches are visible in this aerial view of the pump station, looking straight down.  The two four-foot diameter penstock pipes exiting the left side meet at the Y-shaped pipe and then form one pipe going under a construction access road visible at the far left of the photo.
   
This 48-inch diameter pipe inside the pump station connects to one of the two 28,000 horsepower pump turbines.  The pipe will be completely enclosed by the pump station when work is completed.
   

Workers are preparing to pour concrete to secure the two pump turbines inside the pump station.

 

   
image
Workers created wood forms to prepare for pouring concrete to erect a concrete encasement around a 200-foot section of pipe. The pipe connects the pump station to the 1.25 mile tunnel originating at Olivenhain Reservoir. The encasement and pipe are now located under 25 feet of soil.
   
image
Two 28,000 horsepower pump turbines will move the water in and out of the pump station. Each pump turbine can generate up to 40 Megawatts of energy, enough for 26,000 homes. This photo shows the top of one turbine in place inside the pump station. A centering device used during installation is visible on the top of the head cover.
   
image
In April 2009, community members from the Lake Hodges surrounding communities viewed sample varnish colors on the concrete walls of the pump station. Their preferred color choice was applied to the structure to help blend it in with the natural surroundings. The pump station extends 19 feet above ground and 10 stories below ground.
   
image
A small jib crane will remain on the roof of the pump station. It will be used to lower heavy equipment in and out of the pump station for repairs or maintenance. The crane was painted brown at the recommendation of the Lake Hodges Community Landscape Committee.

 


Electrical Switchyard - Power line and Substation
The electrical switchyard will provide electricity to the pump station and send electricity from the pump station to a local transmission system. As water flows downhill from the Olivenhain Reservoir, it will generate up to 40-megawatts of peak hydroelectric energy, enough power to annually sustain nearly 26,000 homes. This energy will help offset project operating costs and support future Water Authority projects. SDG&E is building one part of the electrical switchyard and the Water Authority will build adjacent equipment.

Electricity generated by the pump turbines will be transmitted to an outdoor switchyard. San Diego Gas & Electric’s construction crews started work on the switchyard in June 2007.

 

This 69kV, ¼-mile-long power line connects the electrical switchyard to the existing San Diego Gas & Electric local transmission system.

 

The San Diego Gas & Electric substation was completed in February 2008. The Water Authority will construct electrical facilities adjacent to the substation prior to the completion of the project.
   

This picture shows an overall view of the construction site with the electrical substation seen in the left foreground.

 


Inlet/Outlet Structure
The Hodges Inlet/Outlet Structure will be located below the surface of Hodges Reservoir. The structure is connected to the pump station by a 200-foot-long tunnel. The pump station will draw or discharge water from the reservoir through the inlet-outlet structure. There will be a trash rack at the west end of the structure that will prevent large debris from entering the pump station. At the east end of the pump station, water travels through a 10-foot diameter underground pipeline to the Olivenhain Reservoir, 1.25 miles away. See graphic at beginning of photo tour section.

 

A cofferdam was constructed around the work site in Hodges Reservoir. The cofferdam is a temporary enclosure from which water is pumped to create a dry area to allow construction of the inlet/outlet tunnel and structure.

 

The inlet/outlet structure was constructed within the walls of the cofferdam. Crews excavated material until they reached the lake bottom.

 

The cofferdam walls were reinforced with shotcrete and rock-bolts, which supported the excavation of the inlet/outlet structure.

   
Pumps inside the cofferdam cells in the dam structure kept the area dry so that workers could install the inlet-outlet structure and tailrace tunnel.
   
image
The cofferdam was completely installed by March 2007. Dismantling began in April 2009. The horse-shoe shaped structure held back the reservoir water while the contractor built the inlet-outlet structure and its connecting tunnel on the lake floor. (photo February 2009)
   
image
Two large cranes were brought on to the site to dismantle the cofferdam. As the cofferdam was dismantled, the components were removed from the site and hauled to a metal scrap yard for recycling. The small rocks that had been inside each cell were removed by an excavator and then used as backfill around the pump station walls.
   
image
Before the contractor could begin dismantling the cofferdam, the entire area had to be flooded so that the water level inside the cofferdam could be the same as the reservoir water level.
   
image
The cofferdam was made of 13 connecting cells of steel sheets and pilings. A crane lifts up one of the pilings from a cell. The pilings extended 5 to 15 feet below the reservoir bottom, depending on their location. At the shoreline, the exposed portion was about 55 feet high.
   
image
A crane lowered a circular template into the center of each cofferdam cell to stabilize it. Then each of the cell’s steel sheets could be removed and the pilings could be pulled out from the reservoir bottom.
   
image
The template is lowered into place and secured.
   
image
During construction for the inlet-outlet structure and related equipment, a string of buoys helped keep boaters from the cofferdam. Connected to the string of buoys was a mesh-like underwater net called a silt curtain, which reduced the amount of underwater dirt that could flow out into the reservoir.
   
image
Once the cofferdam was completely removed in September 2009, the shoreline was stabilized with riprap made of large rocks. A new buoy system was installed (visible red line) to protect the submerged inlet-outlet structure from boaters.