
Photographic
Tour
Construction of the
Lake Hodges Projects began in 2005 and is anticipated to be completed in late
2009. The construction has four components:
• Pipeline Tunnel – a 10-foot diameter underground
pipeline, contained in a 1.25 mile long tunnel, connecting the two reservoirs
• Pump Station – a pump station to move water back
and forth between the two reservoirs and generate electricity
• Electrical Switchyard – an electrical switchyard
providing electricity to the pump station and sending electricity from the pump
station to a local transmission system, SDG&E will build one part and the
Water Authority will build adjacent equipment
• Inlet-outlet Structure – an inlet-outlet structure
below the water surface that draws and discharges water between the Hodges Reservoir
and the pump station
Diagram
of Lake Hodges Projects Components

Pipeline Tunnel
Completed in spring 2007, the pipeline tunnel is 1.25 miles-long and
contains a 10-foot diameter steel pipeline that rises 770 feet in elevation
from Hodges Reservoir to Olivenhain Reservoir.

|
Water will flow back and forth between Hodges and Olivenhain Reservoirs
within this 10-foot diameter steel pipe. The pipe’s epoxy coat protects
the steel pipe from internal corrosion. In total, 148 sections of pipe
were used to complete the tunnel. |
|
|

|
This is a “pipe carrier.” It was used to lift and place the
steel pipe within the 1.25-mile-long pipeline tunnel |
|
|

|
A mucking machine pushes the “pipe carrier” into the pipeline
tunnel. |
|
|
|

|
In this image, the pipe section is placed within the pipeline tunnel and
attached to another installed section of pipe. |
|
|

|
The pipe section is secured inside the pipeline tunnel using timber bracing.
The bracing keeps the pipe from moving and allows the area between the
outside of the pipe and the tunnel wall to be backfilled with grout. |
|
|

|
One by one, each section of pipe is welded together and forms the pipeline
inside the tunnel. |
|
|
|
Once
welded together, the space between the 12-foot diameter tunnel and the
10-foot diameter pipeline is filled with grout. Grout is a fluid material
injected into soil, rock, concrete, or other construction material. Once
hardened, it forms a permanent impervious, watertight bond that provides
structural strength to the pipeline tunnel. This picture shows the grout
being pumped through a grout port installed in the pipe.
|
|
|
|
Construction
crews inspect the inside of the pipeline tunnel prior to completion in
spring 2007. |
|
|
|
Once
completed, the pipeline tunnel was sealed in May 2007. The seal will be
removed when the pump station contractor connects the pump station piping. |
Pump Station
The Hodges Pump Station will extend 12-stories underground and house two 28,000
horsepower pump turbines that will generate 40 megawatts of electricity as water
flows down the pipeline tunnel from Olivenhain Reservoir to Hodges Reservoir.
Electricity generated by the pump turbines will be transmitted to an outdoor
switchyard, then to a 69kV, ¼-mile-long power line that will connect
to the existing local transmission system.

|
Construction equipment and materials used in the tunneling process are
lowered and lifted in and out of the pump station pit using a crane. |
|
|

|
Looking down from the top pump station pit, you can see the excavators
removing material that has been blasted. The material is put in a dumpster-sized
bucket and hauled out of the pit using a crane. |
|
|

|
After construction crews completed excavation of the 12-story Hodges Pump
Station pit in June 2007, construction of the pump station’s foundations,
walls, and floors started. Here, a construction worker places steel reinforcing
bars within the Pump Station floor. The reinforcing bars are encased within
concrete to strengthen and hold the concrete together. |
|
|

|
Construction crews started pouring the foundation of the pump station
in June 2007. Here, concrete is lowered in a large bucket and poured onto
the steel framework. |
|
|

|
Another method of delivering concrete form the top of the pump station
excavation to lower sections was the use of a concrete pump truck. |
|
|

|
As concrete is poured, a construction worker smoothes-over and levels
the concrete with an extension trowel.
|
|
|

|
Here workers smooth and level a floor within the pump station. |
|
|

|
As construction continues within the pump station, steel reinforced walls
are poured. |
|
|

|
Some steel-reinforced concrete walls within the pump station reached ground
level in April 2008. |
|
|

|
As concrete work on floors and walls takes place, some of the water pipes
and equipment is installed. This image captures the installation of equipment
that will house the two pump turbines. The pump turbines will be able
to generate electricity as water flows from Olivenhain into Hodges Reservoir.
The pump turbines will also send water from Hodges Reservoir uphill 1.25
miles to Olivenhain Reservoir. |
|
|

|
Equipment for the Lake Hodges Projects has come from all over the world.
This 98-ton section of pipe is 21 feet in length and width and arrived
on an oversized delivery truck from Fontana, Calif. on May 30. It connects
the pump station to the 1.25-mile-long pipeline between the Hodges and
Olivenhain reservoirs and split the tunnel’s water flow to feed
two pump turbines housed in the pump station. |
Electrical Switchyard
- Powerline and Substation
The electrical
switchyard will provide electricity to the pump station and send electricity
from the pump station to a local transmission system. As water flows downhill
from the Olivenhain Reservoir, it will generate up to 40-megawatts of peak hydroelectric
energy, enough power to annually sustain nearly 26,000 homes. This energy will
help offset project operating costs and support future Water Authority projects.
SDG&E is building one part of the electrical switchyard and the Water Authority
will build adjacent equipment.

|
Electricity generated by the pump turbines will be transmitted to an outdoor
switchyard. San Diego Gas & Electric’s construction crews started
work on the switchyard in June 2007. |
|
|

|
This 69kV, ¼-mile-long power line connects the electrical switchyard
to the existing San Diego Gas & Electric local transmission system. |
|
|

|
The San Diego Gas & Electric substation was completed in February
2008. The Water Authority will construct electrical facilities adjacent
to the substation prior to the completion of the project. |
Inlet/Outlet Structure
The Hodges
Inlet/Outlet Structure will be located below the surface of Hodges Reservoir.
The structure is connected to the pump station by a 200-foot-long tunnel. The
pump station will draw or discharge water from the reservoir through the inlet-outlet
structure. There will be a trash rack at the west end of the structure that
will prevent large debris from entering the pump station. At the east end of
the pump station, water travels through a 10-foot diameter underground pipeline
to the Olivenhain Reservoir, 1.25 miles away. See graphic at beginning of photo
tour section.

|
At the bottom of the pit that will house the pump station, construction
workers drill pilot holes horizontally towards Lake Hodges. This construction
method is referred to as drill & blast method, in which pilot holes
are drilled for explosive charges. Once the explosive charges are set-off,
the resulting debris is carried out and the process is repeated. |
|
|

|
The two-pronged inlet/outlet tunnel will draw or discharge water back
and forth from the inlet/outlet structure, located at the bottom of Hodges
Reservoir, and the pump station. |
|
|

|
A cofferdam was constructed around the worksite in Hodges Reservoir. The
cofferdam is a temporary enclosure from which water is pumped to create
a dry area to allow construction of the inlet/outlet tunnel and structure.
|
|
|

|
The inlet/outlet structure will be located within the walls of the cofferdam.
The structure will be submerged under water when completed. |
|
|

|
The coffer dam walls are reinforced with shotcrete and rock-bolts, which
support the excavation of the inlet/outlet structure. |
|
|

|
Once construction of the inlet/outlet structure is complete, the temporary
cofferdam will be removed. |
|
|

|
The project site -showing the pump station excavation in the foreground
with the coffer dam in the background- is expected to be completed in
late 2009. |
|